Relevant Costing: Make or Buy, Special Orders, and the Costs That Change the Answer
On this page

A special order can be priced below full cost and still increase profit. It can also be priced above variable cost and make the business worse off. The difference is the work the factory gives up to fill it. Before calculating a margin, the candidate has to decide which costs and revenues change.
Relevant costing puts that decision before the arithmetic. The examples below use illustrative US dollars, ignore tax and financing, and compare alternatives over the same short period. They are the sort of operating decisions examined in the US CMA, awarded by the Institute of Management Accountants (IMA).
Which costs belong in the comparison
A relevant amount is a future cost or revenue that differs between alternatives. A sunk cost has already been incurred; changing the decision cannot recover it. An opportunity cost is the benefit sacrificed by choosing one use of a resource over another, even when no invoice records it.
| Amount in the question | Treatment |
|---|---|
| Research already paid for | Exclude the sunk cost. |
| Extra packaging needed for an order | Include the additional expenditure. |
| Fixed overhead allocated to a product | Ask whether total expenditure changes. Allocation alone decides nothing. |
| Contribution lost from displaced sales | Include the opportunity cost. |
Fixed does not mean irrelevant. A supervisor's salary matters if outsourcing removes the position and its cost; it does not if the supervisor stays on the same payroll. Equally, materials already in inventory are not automatically free: regular-use inventory may need replacing, while surplus material may have a resale value that using it sacrifices.
A special order with and without spare capacity
A manufacturer receives a one-off order for 1,000 units at $30 each. The incremental variable cost is $22 a unit. Its normal full cost is $35, including allocated fixed overhead that will remain unchanged. Assume no extra setup, delivery or administration costs and no effect on normal selling prices.
| Order calculation | Spare capacity | Regular sales displaced |
|---|---|---|
| Additional revenue | $30,000 | $30,000 |
| Additional variable cost | ($22,000) | ($22,000) |
| Regular contribution sacrificed | $0 | ($12,000) |
| Change in operating profit | $8,000 increase | $4,000 decrease |
With unused capacity, reject the tempting calculation of $30 less $35: the overhead portion is not an additional payment. With full capacity, the question states that the order displaces regular business earning $12,000 of contribution. That lost contribution reverses the decision.
The minimum price on these assumptions is $22 per unit with spare capacity and $34 with the stated displacement. Neither is a permanent pricing policy. Repeated discounts, customer reactions and future capacity needs require a wider decision than this one-off comparison. The contribution calculation is developed in Cost-Volume-Profit Analysis.
Make or buy, and the use of freed capacity
The same manufacturer needs 5,000 components. A supplier quotes $21 each. Making them requires $16 of variable cost per unit and $20,000 of fixed expenditure that buying would eliminate. Another $30,000 of allocated factory overhead remains under either choice.
| Relevant amount | Make | Buy |
|---|---|---|
| Variable manufacturing cost | $80,000 | $0 |
| Avoidable fixed expenditure | $20,000 | $0 |
| Supplier payment | $0 | $105,000 |
| Total before alternative use | $100,000 | $105,000 |
Making saves $5,000 if the released capacity would stand idle. If buying releases capacity that earns $15,000 of additional contribution, buying improves profit by $10,000: the new contribution exceeds the extra purchase cost. Add that opportunity cost to making, or deduct the benefit from buying, but never do both.
The $30,000 stays outside the comparison because it stays in the business. Supplier reliability, quality, confidentiality and the ability to restart production still matter. A cheaper quote is not enough if it cannot deliver the required component.
Process further, or drop a segment
Once joint production costs have been incurred, allocating them cannot answer whether to process further. Suppose a batch can sell now for $40,000 or after further processing for $55,000, with additional processing costs of $9,000. Further processing adds $6,000: $15,000 of extra revenue less $9,000. The decision is unchanged whether the earlier joint cost allocated to the batch is $10,000 or $30,000.
Dropping a segment uses the same logic. A product line contributes $60,000 before fixed costs, incurs $40,000 of avoidable fixed expenditure and receives $35,000 of common overhead. Its reported loss is $15,000. Closing it saves $40,000 but sacrifices $60,000, reducing total profit by $20,000 if no alternative use exists. The reported loss disappears; the common overhead does not.
How CMA Part 2 asks it
IMA places marginal analysis in Part 2, Section C, Business Decision Analysis. The section carries 25% of the part; that is not a separate weighting for relevant costing. Its learning outcomes include special orders, make or buy, further processing, adding or dropping a segment, and capacity changes.
Practise changing the decisive fact before changing the numbers: idle capacity becomes scarce, a committed salary becomes avoidable, or another use appears. Then state the change in total operating profit. For multi-year equipment decisions, timing and discounting also matter, as explained in Capital Budgeting: NPV, IRR and Payback.
Where to practise this
Prepito's SOCPA Cost, Managerial, and Governmental Accounting course covers differential decision-making. The CMA Part 1 and Part 2 courses open soon and are not yet available for enrolment. Follow the CMA programme page for availability, or use the Part 2 study guide to place these decisions in the syllabus.
Sources: IMA Content Specification Outlines; IMA Learning Outcome Statements, Part 2 C.2; ACCA, Relevant costs. Examples are original and illustrative; confirm the current syllabus before planning an exam sitting.