Flexible Budget vs Static Budget: Separating the Sales-Volume Variance From the Flexible-Budget Variance

A static budget judges actual results against a plan built for a volume the business never reached, so a sales shortfall can make an inefficient factory look thrifty and a sales beat can make an efficient one look wasteful. Flexing the budget to actual output splits the gap in two: the sales-volume variance, and the flexible-budget variance that holds the price, efficiency and spending variances. One month worked end to end, the formulas, and how CMA Part 1, CPA BAR and SOCPA test each layer.
12 min read
On this page
Flexible Budget vs Static Budget: Separating the Sales-Volume Variance From the Flexible-Budget Variance

A factory can use 10% more material and 10% more labour per unit than its standards allow and still send head office a monthly report with every variable cost line under budget. All it needs is for the sales team to miss. That is what a static budget does: it sets actual costs for the 8,000 units the business made against budgeted costs for the 10,000 it planned, and the 2,000 units nobody built show up as savings.

A flexible budget repairs the comparison by restating the plan at the output actually reached, with the same selling price, variable cost per unit and fixed costs. The difference between the static and the flexible budget is the sales-volume variance: what missing or beating the planned volume did to profit. The difference between the flexible budget and actual results is the flexible-budget variance: what prices, efficiency and spending did at the volume achieved. The two add up to the static-budget variance, and IMA's Learning Outcome Statements for the US CMA make each step an outcome of its own.

Below, one month is carried through all three layers, then placed in CMA Part 1, CPA BAR and the SOCPA Fellowship. Every figure is illustrative.

Static budget vs flexible budget: one planned volume or the volume actually reached

The static budget is the master budget as approved: one sales forecast, and every line built from it. It does not move when volume does. Textbooks call it the static, fixed, master or planning budget, and ACCA's Performance Management syllabus speaks of fixed and flexed budgets. The flexible budget keeps the static budget's price per unit, variable cost per unit and total fixed costs, and multiplies the variable lines by actual output. It can be prepared in advance for a range of volumes; for performance analysis it is set at actual output.

VarianceComputed asWhat it isolates
Static-budget varianceActual result minus static budgetEverything at once: volume, prices, efficiency and spending
Sales-volume varianceFlexible budget minus static budget; for operating income, (actual units minus budgeted units) × budgeted contribution margin per unitThe effect of the volume change alone, at budgeted prices and costs
Flexible-budget varianceActual result minus flexible budgetPrices, efficiency and spending at the actual volume

Each difference is labelled by its effect on operating income: favourable (F) if it raises income against the budget, unfavourable (U) if it lowers it. One rule prevents most wrong answers: flex on output, never on inputs. The flexible budget for 8,000 units allows the materials and hours that 8,000 units should need, whatever was used; flexing on the hours actually worked writes the inefficiency into the budget.

Neither is the capital budget, which appraises long-lived investments with discounted cash flows and is covered in Capital Budgeting: NPV, IRR and Payback.

Why a static budget blames the wrong manager

The month: one product, planned at 10,000 units, selling at 50. The standard variable cost is 26 a unit: 2 kg of material at 6 (12), half a labour hour at 20 (10), and variable overhead at 8 per labour hour (4). Fixed costs are 150,000, all factory overhead. Budgeted contribution margin is 24 a unit and budgeted operating income 90,000. The month closes at 8,000 units made and sold, at 51.

LineStatic budget (10,000 units)Actual (8,000 units)Static-budget variance
Revenue500,000408,00092,000 U
Direct materials120,000110,00010,000 F
Direct labour100,00085,80014,200 F
Variable overhead40,00035,6404,360 F
Fixed overhead150,000153,0003,000 U
Operating income90,00023,56066,440 U

Read as it stands, the report says sales lost 92,000 of revenue and the factory saved 28,560 on variable costs. The factory did the opposite. It used 17,600 kg where 8,000 units needed 16,000, and 4,400 hours where they needed 4,000, 10% over on both, and its variable costs were 23,440 above what that output should have cost. The gap between the two stories is 52,000: the 2,000 missing units at 26 of variable cost each, never incurred because the units were never made, and credited to the factory as thrift.

The distortion runs both ways. Had the month closed at 12,000 units with every input exactly at standard, variable costs would have been 312,000 against a static 260,000: a 52,000 unfavourable variance for a factory with no inefficiency at all. When volume falls short of the static budget, variable costs look favourable against it; when volume beats it, they look unfavourable. Neither says how well the inputs were managed.

This is the limitation IMA asks candidates to name at LOS C.1.d. The static budget still answers one question, whether the business sold what it planned, and that answer is the sales-volume variance. It usually belongs to whoever owns demand, though a stock-out or a quality failure in the factory can cause it too.

The three columns: static-budget, sales-volume and flexible-budget variances, worked on one month

Put the flexible budget between the other two and the 66,440 splits. The flexible budget is the static budget's unit figures times 8,000, with fixed overhead unchanged at 150,000.

LineActual (8,000)Flexible-budget varianceFlexible budget (8,000)Sales-volume varianceStatic budget (10,000)
Revenue408,0008,000 F400,000100,000 U500,000
Direct materials110,00014,000 U96,00024,000 F120,000
Direct labour85,8005,800 U80,00020,000 F100,000
Variable overhead35,6403,640 U32,0008,000 F40,000
Contribution margin176,56015,440 U192,00048,000 U240,000
Fixed overhead153,0003,000 U150,0000150,000
Operating income23,56018,440 U42,00048,000 U90,000

Read it from the right. The sales-volume variance is 48,000 U: 2,000 units short at a budgeted contribution margin of 24. The favourable cost figures in that column are not savings but the variable costs of units that did not exist, netted against 100,000 of lost revenue. The flexible-budget variance, 18,440 U, is what happened at 8,000 units: the higher price earned 8,000, and the factory lost 23,440 on variable inputs and 3,000 on fixed overhead. Together they make the 66,440 U.

The order of work is the order of IMA's outcomes: flex first (LOS C.1.e), take the sales-volume variance (C.1.f), then the flexible-budget variance (C.1.g), then open it up (C.1.h). Going straight from actual to static is C.1.c and no further.

Inside the flexible-budget variance: price, efficiency and spending

LOS C.1.h asks you to investigate the flexible-budget variance into differences between actual and budgeted input prices and quantities. The formulas are in Standard Costing and Variance Analysis; this is what they give here.

LineActual inputsPrice, rate or spending varianceEfficiency varianceFlexible-budget variance
Direct materials17,600 kg at 6.254,400 U9,600 U14,000 U
Direct labour4,400 hours at 19.502,200 F8,000 U5,800 U
Variable overhead35,640 over 4,400 hours440 U3,200 U3,640 U
Fixed overhead153,0003,000 UNone3,000 U
Revenue8,000 units at 518,000 F (sales-price variance)None8,000 F
Total2,360 F20,800 U18,440 U

Prices and spending net to 2,360 favourable and efficiency to 20,800 unfavourable: the month's problem was quantities, and the static report booked it as a saving. The labour line shows why variances are read together: a crew paid 0.50 an hour under standard took 10% longer, and a rate saving of 2,200 bought an efficiency loss of 8,000. Variable overhead is driven by labour hours here, so its efficiency variance tracks labour's at 8 an hour.

Fixed overhead behaves differently. Its flexible budget is the static 150,000, because output does not move it, so its whole flexible-budget variance is the spending variance of 3,000 U. If the business also applies fixed overhead under absorption costing, at 150,000 over 10,000 planned units or 15 a unit, the 8,000 units absorb only 120,000 and leave 30,000 of the budgeted 150,000 unabsorbed. That is the production-volume variance, which LOS C.1.r lists separately from the fixed overhead spending variance. It measures planned capacity left idle, not money spent, and it sits outside the flexible-budget variance: adding it to the 18,440 breaks the reconciliation.

The revenue side: sales-price variance, sales-volume variance and where mix enters

On the revenue line the flexible-budget variance is the sales-price variance: (actual price minus budgeted price) × actual units sold, here (51 minus 50) × 8,000 = 8,000 F. Actual units, because the price difference was earned only on units sold.

The sales-volume variance is (actual units minus budgeted units) × a budgeted figure per unit. At the budgeted price of 50 it is a revenue variance, 100,000 U. At the budgeted contribution margin of 24 it is the effect on operating income, 48,000 U, the version the three columns need, because the flexible and static budgets differ only in units and carry the same fixed costs. The figure is always budgeted, never actual: the actual price already sits in the sales-price variance, and actual costs in the cost variances.

Read together, the two tell the story the static report hides. If the move from 50 to 51 is what cost the 2,000 units, the price rise earned 8,000 and lost 48,000 of contribution. That judgement is what the BAR task to interpret sales results by performing price, volume and mix analysis is after.

With more than one product, the sales-volume variance splits again. Suppose the same 10,000 planned units had been two products with a weighted average margin of 24:

ProductBudgeted units (mix)Actual units (mix)Budgeted contribution margin per unit
A6,000 (60%)5,600 (70%)20
B4,000 (40%)2,400 (30%)30
Total10,0008,00024 weighted average

Product by product, the sales-volume variance is (5,600 minus 6,000) × 20 plus (2,400 minus 4,000) × 30: 8,000 U plus 48,000 U, or 56,000 U. The sales-quantity variance prices the total shortfall at the budgeted average margin, (8,000 minus 10,000) × 24 = 48,000 U, the single-product figure. The sales-mix variance applies each product's change in share, at its budgeted margin, to the actual 8,000 units: 10 percentage points more of A at 20 and 10 points less of B at 30 costs 1 a unit, or 8,000 U. The 56,000 is 48,000 of lost units and 8,000 of a shift towards the lower-margin product.

IMA names the sales-mix variance at LOS C.1.n, and ACCA's syllabus asks for the relationship between the sales volume variance and the mix and quantity variances. On the input side, LOS C.1.o and C.1.p add mix and yield variances, which split an input efficiency variance the same way.

How CMA Part 1, CPA BAR and SOCPA test each layer

ExamWhere the analysis sitsHighest skill
US CMA Part 1Section C, Performance Management (20%): C.1.b, LOS C.1.c to C.1.h and C.1.n. Section B (20%): B.4.fLevel C
CPA BARArea I, Business Analysis (40 to 50%): Group A, Topics 1 and 3; Group B, Topic 1Analysis
CPA FARArea I, Financial Reporting (30 to 40%): Group FApplication
SOCPA FellowshipManagement and Governmental Accounting, main topic 2 (26 to 45%): groups 2/8 and 2/1Analysis

IMA's CMA, Part 1

Part 1, Financial Planning, Performance, and Analytics, carries the topic twice. Section B, Planning, Budgeting, and Forecasting (20%), lists flexible budgeting among the budget methodologies at B.4.f with outcomes running from defining it to preparing one. Section C, Performance Management (20%), computes it: C.1.b, use of flexible budgets to analyze performance, whose LOS C.1.c to C.1.h walk this article's path, with C.1.n adding the sales-mix variance. Every Part 1 section is rated Level C, a ceiling that admits questions up to evaluation. The part runs four hours: 100 multiple-choice questions in the first three, then the two case-based questions that replaced the essays from the September 2026 window (China, Taiwan and Japan still sit essays). That hour is explained in CMA Case-Based Questions, and the whole part in the CMA Part 1 Study Guide.

CPA BAR, and one line in FAR

In the CPA Blueprints the topic belongs to BAR, a Discipline section sat only in quarterly testing windows. Area I, Business Analysis, weighted 40 to 50%, tests it in three representative tasks at Analysis. Group A, Topic 1: compare current period financial statement accounts to prior periods or budget and explain variances. Topic 3, managerial and cost accounting: derive the appropriate variance analysis method to measure the key cost drivers by analyzing business scenarios, and interpret sales results by performing price, volume and mix analysis. Group B, Topic 1, adds preparing a budget using supportable assumptions, at Application. BAR allocates nothing to Evaluation, so Analysis is the ceiling.

FAR, a Core section, has one related line in Area I, Group F: calculate variances between budget and actual results, at Application. FAR asks for a variance; BAR asks which variance and what it means. The rest of BAR is in the CPA BAR Study Guide.

SOCPA Management and Governmental Accounting

In the Fellowship the analysis sits in Management and Governmental Accounting, under main topic 2, managerial accounting, weighted 26 to 45%. SOCPA's topic list does not use the phrase flexible budget or name the sales-volume variance. Their home is group 2/8, planning budgets: task 4, analyse the differences between estimated budgets and actual results, at Analysis, beside task 3, apply methods of preparing operating and cash budgets, at Application. The price and efficiency layer is group 2/1, standard costs and cost variances: task 3, analyse variances from standard costs, at Analysis, and tasks 4 to 6 on materials, labour and overhead variances, at Application. The paper is three hours, 36 multiple-choice questions in 108 minutes and then two essay questions in 72, in Arabic or English, and a pass needs 60 out of 100 with at least 5 of the 25 essay marks. Its full map is in the SOCPA Cost, Managerial and Governmental Accounting Study Guide.

Where to practise this

Prepito's CMA Part 1 course and CMA Part 2 course open soon, under the CMA programme. The same analysis can be practised today in two live courses: the BAR course, which covers Area I including budgeting and variance analysis, and the SOCPA Cost, Managerial and Governmental Accounting course, which covers budgets and standard-cost variances for the Fellowship in Arabic and English.

For the layer underneath the flexible-budget variance, read Standard Costing and Variance Analysis; for the contribution margin the sales-volume variance is priced at, Cost-Volume-Profit Analysis.


Every figure in the worked month is illustrative. Sources: IMA CMA Learning Outcome Statements, IMA CMA Content Specification Outlines, effective 1 September 2024, AICPA Uniform CPA Examination Blueprints, AICPA on the Discipline testing windows, SOCPA guidance framework for the Fellowship examinations, SOCPA Fellowship exam structure, SOCPA amendment to the Fellowship exam structure and weights, and the ACCA Performance Management syllabus. IMA, the AICPA and SOCPA revise their outlines and exam formats periodically; confirm the current version for your sitting.

CMA Exam

Activity-Based Costing vs Traditional Costing: Why One Plant-Wide Rate Overcosts the High-Volume Product

A single plant-wide overhead rate charges every product by labour or machine hours, so the simple high-volume line quietly carries the setups and inspections that the complex low-volume line causes. One set of figures costed both ways, the unit, batch, product and facility hierarchy that explains the gap, what IAS 2 lets into inventory, and the pool, driver and rate steps that CMA Part 1, CPA BAR and SOCPA ask you to reproduce.

12 min read

Financial Reporting

The Fair Value Hierarchy Under ASC 820 and IFRS 13: Levels 1, 2 and 3, the Exit Price, and Where the Two Standards Still Part

Fair value is the one topic where US GAAP and IFRS were written together, so the exam does not test a difference; it tests whether you can place an input on the right level and say what the level means. A quoted price in an active market is Level 1, an observable input that is not that price is Level 2, and anything the entity had to assume is Level 3. What the hierarchy ranks (inputs, not techniques), the exit price, the principal market, and what a Level 3 measurement must disclose.

11 min read

Study Planning

Is IFRS 18 on Your Exam? ACCA Already Tests It, the CPA Does Not, and SOCPA Has Not Said When

IFRS 18 has been examinable in ACCA's FR and SBR papers since September 2025 and in DipIFR since December 2025. The CPA tests no IFRS in its 2026 or 2027 Blueprints, IMA's CMA names six IFRS differences and presentation is not one of them, and SOCPA examines IFRS as endorsed in the Kingdom without saying which cycle first examines IFRS 18. One dated table, each body's own timing rule, and how to answer when the date in the question decides.

9 min read

Your cookie choices

Optional cookies help us improve Prepito, measure our ads and personalise advertising. You can change this anytime. Privacy policy